" ... when in his judgment the findings of fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto... "
Cases Decided in the United States Court of Claims ... with Report of ... - Σελίδα 16
των United States. Court of Claims, Audrey Bernhardt - 1950
Πλήρης προβολή - Σχετικά με αυτό το βιβλίο

Cases Decided in the Court of Claims of the United States, Τόμος 111

United States. Court of Claims - 1948 - 886 σελίδες
...extent of delay and his findings of fact therein, a copy of which shall be furnished the contractor, shall be final and conclusive on the parties hereto, subject only to appeal within thirty (30) days by the contractor to the head of the department concerned or his authorized representative,...

Decisions of the Comptroller General of the United States, Τόμος 29

United States. General Accounting Office - 1950 - 710 σελίδες
...the time for completing the work when in his judgment the findings of fact justify such an extension, and his findings of fact thereon shall be final and...authorized representative: whose decision on such appeal us to the facts of delay and the extension of time for completing the work shall be final and conclusive...

Quarters and Allowances at St. Elizabeths Hospital: Hearings, Seventieth ...

United States. Congress. House. Committee on Expenditures in the Executive Departments - 1929 - 266 σελίδες
...cause of delay, who shall ascertain the facts and the extent of the delay, and his findings of facts thereon shall be final and conclusive on the parties...contractor to the head of the department concerned, whose decision on such appeal as to the facts of delay shall be final and conclusive on the parties...

Quarters and Allowances at St. Elizabeths Hospital: Hearings Before the ...

United States. Congress. House. Committee on Expenditures in the Executive Departments - 1929 - 252 σελίδες
...cause of delay, who shall ascertain the facts and the extent of the delay, and his findings of facts thereon shall be final and conclusive on the parties...contractor to the head of the department concerned, whose decision on such appeal as to the facts of delay shall be final and conclusive on the parties...

Decisions of the Comptroller General of the United States, Τόμος 8

United States. General Accounting Office - 1929 - 804 σελίδες
...of delay, who shall ascertain the facts and the extent of the delay, and his findings of facts there shall be final and conclusive on the parties hereto, subject only to appeal, within thirty days, by the contractor to the head of the department concerned, whose decision oil such appeal...

Specifications, Schedule, and Drawings: Hoover Dam, Power Plant and ...

United States. Bureau of Reclamation - 1930 - 132 σελίδες
...delay, who shall ascertain the facts and the (4) ю-im extent of the delay, and his findings of facts thereon shall be final and conclusive on the parties hereto, subject only to appeal, within thirty days, by the contractor to the head of the department concerned, whose decision on such appeal...

Orders and Regulations, Corps of Engineers, U.S. Army, 1934

United States. Army. Corps of Engineers - 1934 - 396 σελίδες
...excusable delay, as hereinafter defined. The contracting officer shall ascertain the cause of the delay, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject to appeal within thirty (30) days by the contractor to the Secretary of War or his duly authorized...

Congressional Serial Set, Τεύχος 9878

1935 - 1036 σελίδες
...contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of delay and his findings of fact thereon shall be final and...contractor to the head of the department concerned, whose decision on such appeal as to the facts of delay shall be final and conclusive on the parties...

The Code of Federal Regulations of the United States of America ..., Βιβλίο 2

1939 - 1306 σελίδες
...such notification from the Contractor, the Contracting Officer shall ascertain the cause of the delay, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject to appeal within thirty days by the Contractor to the Secretary of War or his duly authorized representative,...

The Code of Federal Regulations of the United States of America ..., Βιβλίο 1

1944 - 1386 σελίδες
...such notification from the Contractor, the Contracting Officer shall ascertain the cause of the delay, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject to appeal within thirty days by the Contractor to the Secretary of War or his duly authorized representative,...