| United States. Court of Claims, Audrey Bernhardt - 1955 - 908 σελίδες
...the Contractor, or any other Subcontractor, through no default of the Subcontractor, then the time fixed for the completion of the work shall be extended for a period equivalent to the time lost by any or all of the causes aforesaid, but no such 501 Findings of Fact allowance shall be made unless... | |
| British Columbia - 1913 - 696 σελίδες
...other unavoidable causes, then the time herein fixed for the doing or completion of any such works shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid. The period of such extension shall, if the City and Railway Company or the... | |
| 1917 - 2042 σελίδες
...or cyclone, or by the abandonment of the work by the employes through no fault of the subcontractor, then the time herein fixed for the completion of the...equivalent to the time lost by reason of any or all of the causes aforesaid," etc. This provision makes it clear that delays occasioned the plaintiff by... | |
| 1907 - 2094 σελίδες
...lightning, earthquake or cyclone, or by strikes or lockouts, through no default of the contractor, then the time herein fixed for the completion of the...equivalent to the time lost by reason of any or all of the causes aforesaid, but no such allowance shall be claimed or made unless a claim therefor shall... | |
| 1905 - 1156 σελίδες
...work by the act, neglect, delay, or default of the owner or the architects, » • • then the time fixed for the completion of the work shall be extended...equivalent to the time lost by reason of any or all of the causes aforesaid, but no such allowance shall be made unless a claim therefor is presented in... | |
| 1914 - 1134 σελίδες
...architects or of any other contractor employed by the owner on the work, the time fixed for completion "shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid." But It was' also provided that "no such allowance will be made unless a claim... | |
| 1902 - 1270 σελίδες
...abandonment of the work by the employC-s of the contractor through no fault of theirs, then the time fixed for the completion of the work shall be extended for a period equivalent to the time thus lost," etc. It thus appears that the contractors stipulated what they might claim for themselves... | |
| 1912 - 1356 σελίδες
...prosecution or completion of the work by the act, neglect, or default of the owner or architect that the time herein fixed for the completion of the work shall be extended for a period equal to the time lost by reason of any such cause. But It also provides that no such allowance shall... | |
| 1906 - 1292 σελίδες
...the owner or the architects, or of any other contractor employed by the owner upon the work, * * * then the time herein fixed for the completion of the work shall be extended," etc. The undisputed evidence shows that the contract ] with the brick company was made by the contractors... | |
| 1915 - 1242 σελίδες
...resulting from default or collusion on the part of the contractor, then the time herein fixed for (he completion of the work shall be extended for a period...equivalent to the time lost by reason of any or all of the causes aforesaid. *• * * " The contractor did employ union labor, as he had agreed to do ;... | |
| |