The Federal Reporter, Τόμος 319West Publishing Company, 1963 |
Αναζήτηση στο βιβλίο
Αποτελέσματα 1 - 3 από τα 58.
Σελίδα 140
... COMPLETION : The Govern- ment shall have the right to take possession of or use any completed or partially completed part of the work . Such possession or use shall not be deemed an acceptance of any work not completed in accordance ...
... COMPLETION : The Govern- ment shall have the right to take possession of or use any completed or partially completed part of the work . Such possession or use shall not be deemed an acceptance of any work not completed in accordance ...
Σελίδα 150
... completed and had their elec- trical connections and everything in- stalled ? " ' A. No. I think we realized it was not totally completed , however I will say this , that when a plant is ready to be turned over to us for op- eration ...
... completed and had their elec- trical connections and everything in- stalled ? " ' A. No. I think we realized it was not totally completed , however I will say this , that when a plant is ready to be turned over to us for op- eration ...
Σελίδα 210
... completed by Burns in " the latter part of July , 1949 " . In the first part of August , 1949 , Burns assisted Barton in building a second " burst maker " which was completed " about the middle of August . " Con- cerning the testing and ...
... completed by Burns in " the latter part of July , 1949 " . In the first part of August , 1949 , Burns assisted Barton in building a second " burst maker " which was completed " about the middle of August . " Con- cerning the testing and ...
Άλλες εκδόσεις - Προβολή όλων
Συχνά εμφανιζόμενοι όροι και φράσεις
action affirmed agreement alleged amended appellant appellant's appellee application Attorney bargaining Brown & Root CCPA charge Chief Judge Circuit Judge Cite as 319 claims Company construction contract contractor conviction Corp corporation counsel counts Court of Appeals Criminal decision defendant defendant's denied disclosed District Court District Judge double patenting employees engine epoxy evidence F.Supp fact federal filed funds Government guilty habeas corpus heating plant held invention issue judgment June jurisdiction jury KEY NUMBER SYSTEM L.Ed ment methyl isothiocyanate motion National Labor Relations negligence operation opinion parties patent payment petition petitioner phosgenation plaintiff prior art question reason record reduction to practice rejection rule S.Ct Section sentence sion specific SPENCER BELL statement statute supra Supreme Court testified testimony tion trial court trial judge U. S. Atty union United States Court United States District verdict violation Washington WNDR WSYR York