... ment , pumps , valves , other auxiliaries , and the distribution system . ture of the system was the automatic controls to be operated electrically . The central heating plant covered by appel- lant's contract included two boilers which ...
... ment , pumps , valves , other auxiliaries , and the distribution system . ture of the system was the automatic controls to be operated electrically . The central heating plant covered by appel- lant's contract included two boilers which ...
Σελίδα 176
... ment under Modification No. 10 was an accord and satisfaction completely dis- charging plaintiffs ' claim for damages due to excessive delays in obtaining Gov- ernment - supplied equipment . We think defendant is correct . Modification ...
... ment under Modification No. 10 was an accord and satisfaction completely dis- charging plaintiffs ' claim for damages due to excessive delays in obtaining Gov- ernment - supplied equipment . We think defendant is correct . Modification ...
Σελίδα 178
... ment with the contractor settling a claim for unliquidated damages flowing from Government delays , and the agreed amount is actually paid from funds ap- propriated for that procurement , such settlement is conclusive of all elements of ...
... ment with the contractor settling a claim for unliquidated damages flowing from Government delays , and the agreed amount is actually paid from funds ap- propriated for that procurement , such settlement is conclusive of all elements of ...
Άλλες εκδόσεις - Προβολή όλων
Συχνά εμφανιζόμενοι όροι και φράσεις
action affidavit affirmed agreement alleged amended appellant appellant's appellee application Attorney bargaining Brown & Root CCPA charge Chief Judge Circuit Judge Cite as 319 claims Company compound construction contract contractor conviction Corp corporation counsel counts Court of Appeals Criminal decision defendant defendant's denied disclosed District Court District Judge double patenting employees engine epoxy Esperdy evidence F.Supp fact federal filed funds Government guilty habeas corpus heating plant held invention issue judgment June jurisdiction jury KEY NUMBER SYSTEM L.Ed ment methyl isothiocyanate motion National Labor Relations negligence operation opinion parties patent payment petition petitioner phosgenation plaintiff prior art proceeding question reason record reduction to practice rejection rule S.Ct Section sentence sion specific SPENCER BELL statement statute supra Supreme Court testified testimony tion trial court U. S. Atty union United States Court United States District verdict violation Washington York