... estimate a value of S using whatever informa- tion is available . Assume the estimate is S = 0.02 . This leads to k = 3.0 . Entering Exhibit IV.4-2 , proceed vertically along the k = 3.0 line until reaching the P = .90 curve . Reading ...
... estimate a value of S using whatever informa- tion is available . Assume the estimate is S = 0.02 . This leads to k = 3.0 . Entering Exhibit IV.4-2 , proceed vertically along the k = 3.0 line until reaching the P = .90 curve . Reading ...
Σελίδα 163
... estimated and compared to a critical value M. Only Form 2 is presented for the double - specification limits case in ... Estimation of the fraction defective is required to make decisions on the acceptability of lots when using Form 2 ...
... estimated and compared to a critical value M. Only Form 2 is presented for the double - specification limits case in ... Estimation of the fraction defective is required to make decisions on the acceptability of lots when using Form 2 ...
Σελίδα 178
... estimate of the population standard deviation σ , and since standard values for variability will frequently be given in terms of o , a conversion factor is required . ( The reader might recall that S2 is an unbiased estimate of o2 ...
... estimate of the population standard deviation σ , and since standard values for variability will frequently be given in terms of o , a conversion factor is required . ( The reader might recall that S2 is an unbiased estimate of o2 ...
Περιεχόμενα
Useful Probability Distributions | 15 |
71 x² Values for Given Tail Areas | 60 |
Hypothesis Testing | 73 |
Πνευματικά δικαιώματα | |
19 άλλες ενότητες δεν εμφανίζονται
Άλλες εκδόσεις - Προβολή όλων
Handbook of Tables and Graphs for the Industrial Engineer and Manager Jerry Banks,Russell G. Heikes Προβολή αποσπασμάτων - 1984 |
Συχνά εμφανιζόμενοι όροι και φράσεις
A/P r,n Ac Re Ac amount Factor worth average lead binomial distribution code letter computed confidence interval control charts control limits critical values degrees of freedom direct labor hours economic order quantity Entering Exhibit Equal Payment Series Example C-1 Exhibit II.3-1 exponential distribution F To Find F/P r,n P/F Factor amount Factor Factor To Find Factor worth Factor Find A Given Find F fraction defective function Given F Given Given P F/P H₁ inches integer INTEREST FACTORS lead time demand median MTBF n₂ nomogram nomograph normal distribution normal population null hypothesis Payment Equal Payment Payment Series Compound percent Poisson Poisson distribution probability of acceptance procedure quality control random numbers random variable Reading the Tables Right-Hand Tail sample size SAMPLE SIZES scale Section Single Payment Equal specified standard deviation Tables Example B-1 test statistic TESTS ON MEANS units variance απ