" Should the Contractor be delayed in the prosecution or completion of the work by the act, neglect or default of the Owner , of the Architect , or of any other contractor employed by the Owner upon the work, or by any damage caused by fire or other casualty... "
The Southwestern Reporter - Σελίδα 448
1909
Πλήρης προβολή - Σχετικά με αυτό το βιβλίο

Reports of Cases at Law and in Chancery Argued and Determined in ..., Τόμος 255

Illinois. Supreme Court - 1913 - 712 σελίδες
...liquidated damages. Following the agreement for damages for delay was this provision : "Art. VII. — Should the contractor be delayed in the prosecution...owner upon the work, or by any damage caused by fire or other casualty for which the contractor is not responsible, or by general strikes or lockouts caused...

Reports of Cases at Law and in Chancery Argued and Determined in ..., Τόμος 228

Illinois. Supreme Court - 1908 - 710 σελίδες
...or completion of his work by the act, neglect, delay or default of the owner or the superintendent, or of any other contractor employed by the owner upon the work, or by damages which may happen by fire, lightning, earthquake or cyclone, or by abandonment of the work by...

Cases Decided in the United States Court of Claims ... with ..., Τόμος 131

United States. Court of Claims, Audrey Bernhardt - 1955 - 908 σελίδες
...$320,000. The subcontract provided, in part, as follows: If the Subcontractor shall be obstructed or delayed in the prosecution or completion of the work * * * by the act, neglect or default of the Contractor, or the Findings of Fact Owner, or of any other Subcontractor employed by or dealing with...

Arkansas Reports: Cases Determined in the Supreme Court of the ..., Τόμος 104

Arkansas. Supreme Court - 1913 - 694 σελίδες
...be completed on or before the 1st day of November, 1909. Article 7 provides that, if the contractors be delayed in the prosecution or completion of the work by the act, neglect or default of the owner or architect the time herein fixed for the completion of the work shall be extended for a period equal...

The New York Supplement, Τόμος 150

1915 - 1242 σελίδες
...strikes and disagreements during the performance of this contract." It was further provided that : "Should the contractor be delayed in the prosecution or completion of the work by * * * combined action of workmen in no wise resulting from default or collusion on the part of the...

Stone; an Illustrated Magazine, Τόμος 6

1893 - 814 σελίδες
...prosecution or completion of his work by the act, neglect, delay or default of the Owner, or the Architects, or of any other contractor employed by the Owner upon the work, or by any damage which may happen by fire, lightning, earthquake or cyclone, or by the abandonment of the work by the...

Architect, Owner and Builder Before the Law: A Summary of American and ...

Theodore Minot Clark - 1894 - 432 σελίδες
...prosecution or completion of his work by the neglect, delay, or default of the Owner, or the Architects, or of any other contractor employed by the Owner upon the work, or by any damage which may happen by fire, lightning, earthquake or cyclone, or by the abandonment of the work by the...

Architect, Owner and Builder Before the Law: A Summary of American and ...

Theodore Minot Clark - 1894 - 424 σελίδες
...prosecution or completion of his work by the neglect, delay, or default of the Owner, or the Architects, or of any other contractor employed by the Owner upon the work, or by any damage which may happen by fire, lightning, earthquake or cyclone, or by the abandonment of the work by the...

Official Report ... Annual Convention, Τόμος 8,Μέρος 1894

National Association of Builders of the United States of America - 1894 - 274 σελίδες
...or completion of this work by the act, neglect, delay, or default of the Owner, or the Architects, or of any other Contractor employed by the Owner upon the work, or by any damage which may happen by fire, lightning, earthquake, or cyclone, or by the abandonment of the work by the...

Electric Lighting Specifications

Earle Abbott Merrilol - 1896 - 232 σελίδες
...prosecution or completion of his work by the act, neglect, delay or default of the Owner, or the Architects, or of any other contractor employed by the Owner upon the work, or by any damage which may happen by fire, lightning, earthquake or cyclone, or by the abandonment of the work by the...