Should the Contractor be delayed in the prosecution or completion of the work by the act, neglect or default of the Owner , of the Architect , or of any other contractor employed by the Owner upon the work, or by any damage caused by fire or other casualty... The Southwestern Reporter - Σελίδα 4481909Πλήρης προβολή - Σχετικά με αυτό το βιβλίο
| Wilbur Jay Watson - 1908 - 92 σελίδες
...thereof shall be conclusive upon the parties, subject to the Arbitration Clause. See Art. 237.) 234. Should the Contractor be delayed in the prosecution...by the act, neglect or default of the Owner, of the Engineer, or of any other Contractor employed by the Owner upon the work, or by damage caused by fire... | |
| 1909 - 474 σελίδες
...comprehended in this agreement by and at the time or times hereinafter stated , to wit : ART. VII. Should the Contractor be delayed in the prosecution...the Owner upon the work, or by any damage caused by Ore, lightning, earthquake, cyclone or other casualty for which the Contractor not responsible, or... | |
| Connecticut. Office of the Attorney General - 1909 - 304 σελίδες
...causes, the contract provides as follows : "Art. VII. Should the contractor be delayed in the prosecution of the work by the act, neglect or default of the...of any other contractor employed by the owner upon such work, or by any damage caused by fire or other casualty for which the Contractor is not responsible,... | |
| Massachusetts. Supreme Judicial Court - 1909 - 782 σελίδες
...in the prosecution or completion of bis work by the act, neglect, delay or default of the Owner, or the Architect, or of any other Contractor employed by the Owner upon the work, or by any damage which may happen by fire, lightning, earthquake or cyclone, or by the abandonment of the work by the... | |
| Charles Evan Fowler - 1909 - 180 σελίδες
...prosecution or completion of his work by the act, neglect, delay or default of the Owner, or the Architects, or of any other contractor employed by the Owner upon the work, or by any damage which may happen by fire, lightning, earthquake or cyclone, or by the abandonment of the work by the... | |
| Edward Betley Brown, L. S. Le Vernois, Esten Kenneth Williams - 1909 - 760 σελίδες
...the work was 12th June, 1907, but it contains a stipulation that should the contractor be obstructed in the prosecution or completion of the work by the act, neglect, or delay of the owner or architect, or by reason of sundry other matters therein specified, the time fixed... | |
| 1909 - 1316 σελίδες
...the Employes' Association. With respect to strikes and lockouts the contract provided as follows : "Should the contractor be delayed In the prosecution or completion of the work l,y the art, neglect or default of the owner or the architects or of any other contractor employed... | |
| William A. Radford, Alfred Sidney Johnson - 1909 - 446 σελίδες
...contractor released from the time insurance feature of this contract, if he is delayed in the prosecution of the work by the act, neglect, or default of the owner or of anyone employed by Him or by any outside agency the responsibility for which is not traceable... | |
| 1910 - 472 σελίδες
...comprehended In this agreement by and at the time or times hereinafter stated , to wit : ART. VII. Should the Contractor be delayed in the prosecution...the Owner upon the work, or by any damage caused by tiro, lightning, earthquake, cyclone or other casualty for which the Contractor — not responsible,... | |
| New York (State). Supreme Court. Appellate Division - 1910 - 1092 σελίδες
...employers' association. "With respect to strikes and lockouts the contract provided as follows : " Should the contractor be delayed in the prosecution...by the act, neglect or default of the owner, of the architects, or of any other contractor employed by the owner upon the work, or by any damage caused... | |
| |