| United States. Supreme Court - 1947 - 988 σελίδες
...contracts with the United States, each of which provided that "disputes concerning questions arising under this contract shall be decided by the contracting officer . . . subject to written appeal ... to the head of the department." Held: 1. Disputes as to extra pay for footing excavations and for... | |
| United States. Supreme Court - 1947 - 978 σελίδες
...contracts -vith the United States, each of which provided that "disputes concerning questions arising under this contract shall be decided by the contracting officer . . . subject to written appeal ... to the head of the department." Held: 1. Disputes as to extra pay for footing excavations and for... | |
| United States. Congress. Joint Committee on Housing - 1948 - 1564 σελίδες
...the purchaser for the purpose of securing business. 7. Disputes concerning questions of fact arising under this contract shall be decided by the contracting officer, subject to written appeal by the purchaser to the Secretary of the Navy, within 30 days following receipt by the purchaser of the written... | |
| United States. Department of the Interior, Ray Lyman Wilbur, Northcutt Ely - 1948 - 1144 σελίδες
...Contracting Officer, subject to written appeal by the City within 30 days to the Secretary of the Navy or his duly authorized representative, whose decision shall be final and conclusive. Pending decision, the City shall diligently proceed with performance. ARTICLE 10. NONDISCRIMINATION... | |
| 1949 - 906 σελίδες
...otherwise specifically provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting...concerned or his duly authorized representative, whose decisions shall be final and conclusive upon the parties thereto. In the meantime the contractor shall... | |
| 1949 - 738 σελίδες
...otherwise specifically provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting...concerned or his duly authorized representative, whose decisions shall be final and conclusive upon the parties thereto. In the meantime the contractor shall... | |
| United States - 1945 - 1036 σελίδες
...as otherwise provided, all disputes concerning questions of fact arising under the contract should be decided by the contracting officer subject to written...contractor within 30 days to the head of the department, whose decision should be conclusive on the parties, was valid. American Engineering Co. v. US (DC,... | |
| 1966 - 502 σελίδες
...provided in the contract, all disputes concerning questions of fact arising under §10.1 §11.1 the contract shall be decided by the contracting officer...written appeal by the contractor within 30 days to the Secretary or his duly authorized representative, whose decision shall be final and conclusive upon... | |
| |