Κρυφά πεδία
Βιβλία Βιβλία
" Claims for loss, damage, or delay must be made in writing to the carrier at the point of delivery or at the point of origin within four months after delivery of the property, or, in case of failure to make delivery then, within four months after a reasonable... "
The Pacific Reporter - Σελίδα 368
1917
Πλήρης προβολή - Σχετικά με αυτό το βιβλίο

Reports of Cases Heard and Determined in the Appellate Division ..., Τόμος 175

New York (State). Supreme Court. Appellate Division - 1917 - 1196 σελίδες
...bill of lading provides, among other things, as follows: "Claims for loss, damage or delay must be made in writing to the carrier at the point of delivery...or at the point of origin within four months after the delivery of the property, or, in case of failure to make delivery, then within four mouths after...

Reports of Cases Heard and Determined in the Appellate Division ..., Τόμος 192

New York (State). Supreme Court. Appellate Division - 1921 - 1118 σελίδες
...whether or not such loss or damage occurs from negligence. " Claims for loss, damage, or delay must be made in writing to the carrier at the point of delivery or at the point of origin within four months afxer delivery of the property, or, in case of failure to make delivery, then within four months after...

Reports of Cases Heard and Determined in the Appellate Division ..., Τόμος 187

New York (State). Supreme Court. Appellate Division - 1919 - 1124 σελίδες
...while being loaded or unloaded, or damage in transit by carelessness or negligence, claims must be made in writing to the carrier at the point of delivery or at tho point of origin within four months after delivery' of the property, or, in case of failure to make...

Proceedings of the ... Annual Conference of Commissioners on ..., Τόμος 18

Commissioners on Uniform State Laws (U.S.). Conference - 1908 - 178 σελίδες
...whether or not such loss or damage occurs from negligence. Claims for loss, damage, or delay must be made in writing to the carrier at the point of delivery...after a reasonable time for delivery has elapsed. Unless claims are so made the carrier shall not be liable. Any carrier or party liable on account of...

Year Book

Merchants' Association of New York - 1920 - 1096 σελίδες
...condition : "Suits for loss, damage, or delay shall be instituted only within two years and one day after delivery of the property, or in case of failure to make delivery, then within two years and one day after a reasonable time for delivery has elapsed." For some time after the two...

Report

Railroad Commission of Ohio - 1908 - 578 σελίδες
...whether or not such loss or damage occurs from negligence. Claims for loss, damage, or delay must be made in writing to the carrier at the point of delivery...after a reasonable time for delivery has elapsed. Unless claims are so made the carrier shall not be liable. Any carrier or party liable on account of...

Annual Report of the American Bar Association: Including ..., Τόμος 33

American Bar Association - 1908 - 1138 σελίδες
...whether or not such loss or damage occurs from negligence. Claims for loss, damage, or delay must be made in writing to the carrier at the point of delivery...after a reasonable time for delivery has elapsed. Unless claims are so made the carrier shall not be liable. Any carrier or party liable on account of...

Report of the Commissioner of Corporations on Transportation by Water in the ...

United States. Bureau of Corporations - 1909 - 648 σελίδες
...whether or not such loss or damage occurs from negligence. Claims for loss, damage, or delay must be made in writing to the carrier at the point of delivery...after a reasonable time for delivery has elapsed. Unless claims are so made, the carrier shall not be liable. Any carrier or party liable on account...

Interstate Commerce Commission Reports: Reports and Decisions of the ...

United States. Interstate Commerce Commission - 1909 - 908 σελίδες
...whether or not such loss or damage occurs from negligence. Claims for loss, damage, or delay must be made in writing to the carrier at the point of delivery...or at the point of origin within four months after deliver}7 of the property, or, in case of failure to make delivery, then within four months after a...

Railroad Traffic and Rates: The freight service

Emory Richard Johnson, Grover Gerhardt Huebner - 1911 - 620 σελίδες
...maximum amount to govern such computation, whether or not such loss or damage occurs from negligence. Claims for loss, damage, or delay must he made in...within four months after delivery of the property, or, incase of failure to make delivery, then within lour months after a reasonahie time for delivery lias...